Here's a little construction tale from last week. The Client wanted a 10x3m deck built in 3 days due to him needing the space ready.

We started off slowly because the space because was very tight, had no time or room to bust holes in the concrete and install posts/bearers as you would normally do. Instead I bracketed the joists straight to the concrete slab. As it dropped down I was able to put a bearer in.