Our discussion today is the calculation of labor requirements and floor work materials, this flooring work includes backfill work, K-100 cast concrete, landfill sand and floor coating (ceramic size 40 x 40 cm).
At this early stage we should know in advance technical backfill work, landfill sand, K-100 cast concrete and floor coating.
a. Backfill work
The soil used must meet the technical specifications, the backfill compaction is done by means or manually, the backfill overlap is done by not accumulating in a particular field to facilitate the worker in the process of overlaying.
b. Landfill sand
The landfill sand in question is layered in layers and compacted manually or by means.
c. Concrete (K-100)
The foundry work begins by mixing the material in accordance with the specification until it becomes homogeneous, after the concrete mixture is stirred, it is poured into a bucket or a stroller and overlaid on the floor surface, when casting needs to be compacted by pounding the surface with wood so that cast gravel can be mutually filling and solid, on the surface that has been considered flat need to be made rough with broom stick.
d. Floor coating (Ceramic size 40 x 40 cm)
Floor coating work that we will discuss is ceramic floor size 40 x 40 cm, this work started after the work of the cast floor is considered finished.
Ceramics will be lined with a layer of water mixed with cement, this mixture serves as a glue between the ceramic and the cast floor.
After the ceramic is dry and considered finished then the worker then insert ceramic gap with color cement so that ceramic not quickly damaged during expansion.
The use of ceramic floor is very common in Indonesia, ceramics have high flexibility and can be used in almost all rooms.
Another plus is, ceramic does not require polishing and has a low maintenance cost.
Currently ceramic is very easy to find on the market, various colors and textures we can choose to make ceramics cheap choice of users.
a. Backfill
Is known :
Items | Information |
---|---|
Length | 2.00 m |
Width | 2.00 m |
Height | 0.22 m |
Answer:
Items | Amount |
---|---|
Length x Width x Height | m3 |
2.00 x 2.00 x 0.22 | 0.88 m3 |
Total amount | 0.88 m3 |
c. Landfill Sand
Is known :
Items | Information |
---|---|
Length | 2.00 m |
Width | 2.00 m |
Height | 0.05 m |
Answer:
Items | Amount |
---|---|
Length x Width x Height | m3 |
2.00 x 2.00 x 0.05 | 0.20 m3 |
Total amount | 0.20 m3 |
c. Concrete K-100
Is known :
Items | Information |
---|---|
Length | 2.00 m |
Width | 2.00 m |
Height | 0.05 m |
Answer:
Items | Amount |
---|---|
Length x Width x Height | m3 |
2.00 x 2.00 x 0.05 | 0.20 m3 |
Total amount | 0.20 m3 |
d. Floor Coating (Ceramic Size 40 x 40 cm)
Is known :
Items | Information |
---|---|
Length | 2.00 m |
Width | 2.00 m |
Answer:
Items | Amount |
---|---|
Length x Width | m2 |
2.00 x 2.00 | 4.00 m2 |
Total amount | 4.00 m2 |
I use technical analysis in accordance with the Indonesian National Standard to determine the required labor and material requirements for floor work with an area of 4.00 M 2
a. Backfill work
To work on 1m3 backfill jobs is required:
Items | Amount |
---|---|
Worker | 0.300 Person Per Day |
Overseer | 0.010 Person Per Day |
Land | 1,200 m3 |
To do backfill work with a volume of 0.88 m3 is required
Items | Information | Amount |
---|---|---|
Workers | 0.300 Person Per Day x 0.88 m3 | 0.264 Person |
Overseer | 0.010 Person Per Day x 0.88 m3 | 0.009 Person |
Ground | 1,200 m3 x 0.88 m3 | 1.056 m3 |
c. Concrete Work K-100
To work on 1m3 of K-100 concrete work is required:
Items | Amount |
---|---|
Worker | 1,200 Person Per Day |
Stonemason | 0,200 Person Per Day |
Foreman | 0.020 Person Per Day |
Overseer | 0.060 Person Per Day |
Portland Cement | 230,000 Kg |
Concrete Sand | 893,000 Kg |
Gravel | 1,027,000 Kg |
Water | 200,000 Liter |
To do the work of K-100 concrete with a volume of 0.20 m3 is required
Items | Information | Amount |
---|---|---|
Worker | 1,200 Person Per Day x 0.20 m3 | 0.240 Person |
Stonemason | 0,200 Person Per Day x 0.20 m3 | 0.040 Person |
Foreman | 0.020 Person Per Day x 0.20 m3 | 0.004 Person |
Overseer | 0.060 Person Per Day x 0.20 m3 | 0.012 Person |
Portland Cement | 230,000 Kg x 0.20 m3 | 46,000 Kg |
Concrete Sand | 893,000 Kg x 0.20 m3 | 178,600 Kg |
Gravel | 1,027,000 Kg x 0.20 m3 | 205,400 Kg |
Water | 200,000 Liter x 0.20 m3 | 40,000 Liter |
d. Floor coating work (Ceramic size 40 x 40 cm)
To work 1m2 of concrete work Floor coating (Ceramics size 40 x 40 cm) is required:
Items | Amount |
---|---|
Worker | 0.250 People Per Day |
Floorman | 0.125 People Per Day |
Foreman | 0.013 People Per Day |
Overseer | 0.013 Person Per Day |
Ceramics Floor 40x40 cm | 1.060 m2 |
Portland Cement | 9,800 Kg |
Cement Colors | 1,300 Kg |
Sand | 0.045 m3 |
To do floor cover work with an area of 4.00 m2 is required
Items | Information | Amount |
---|---|---|
Worker | 0.250 Person Per Day x 4,00 m2 | 1,000 Person |
Floorman | 0.125 Person Per Day x 4,00 m2 | 0,500 Person |
Foreman | 0.013 Person Per Day x 4,00 m2 | 0.052 Person |
Overseer | 0.013 Person Per Day x 4,00 m2 | 0.052 Person |
Ceramics Floor 40x40 cm | 1.060 m2 x 4,00 m2 | 4,240 m2 |
Portland Cement | 9,800 Kg x 4,00 m2 | 39,200 Kg |
Cement Colors | 1,300 Kg x 4.00 m2 | 5,200 Kg |
Sand | 0.045 m3 x 4.00 m2 | 0.180 m3 |
To do the floor coating work in accordance with the above picture is required:
Items | Amount |
---|---|
Worker | 1,564 Person |
Stonemason/Floorman | 0,540 Person Per Day |
Foreman | 0,056 Person Per Day |
Overseer | 0,075 Person Per Day |
Soil | 1,056 m3 |
Sand Landfill | 0,240 m3 |
Portland Cement | 85,200 Kg |
Concrete Sand | 178,600 Kg |
Gravel | 205,400 Kg |
Water | 40,000 Liters |
Ceramics Floor 40x40 cm | 4,240 m2 |
Cement Colors | 5,200 Kg |
Sand | 0,180 m3 |
The calculation of the need for floor work is just an example and can be used especially to young engineers and lay people, analysis of labor and material needs calculations on this work using the analysis of Indonesian National Standard, can be developed as needed.
This is all I can write right now, for all the lack of writing and as a servant of God I apologize.
Thanks to friends who have visited this blog and are willing to provide constructive comments, as well as to all science persons who are willing to sacrifice their time to create a better human civilization.
source:
www.wikipedia.org-Soil compaction
www.wikipedia.org-Earth structure
www.wikipedia.org-Urugan tanah
www.wikipedia.org-Technical analysis
Do you love science? then join us at steemstem using @science tags and @steemstem, you can also chat with us at steemstem chat. channel.
Best regards @kharrazi
its very good post and explenation mr. @kharrazi, thanks for sharing at your blog,,,,,,......!!!
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
my pleasure, thanks for visiting my blog.
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
This is crazy. I never imagined it would need so much material... cool
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
no @moobs, that's three digits behind the comma, decimal three digits :D
Thanks for your visiting
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
moobs...
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
@mobbs...
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit