I dont know if your up to date with the biggest Graveyard for Taxpayers in Germany the"BER" prestige objekt from the Goverment
This Airport (at the moment only Birds flying there) was expected to open in June 2012.
One missmanegment is looking for the better one witch tops it
Yesterday NTV was telling that 750 (sevenhunderdfifty) Monitors have to be changed
Because they was insatalld for the planned opening and they was on the electric since than.
Now they all have to be replaced because after 6 Years ther lifetime is over
Cost for the Taxpayers Half Million Euro
Here is the original Text from NTV
ImHauptterminal müssen 750 Monitore für die Fluggastinformation ausgetauscht werden. Die Bildschirme seien sechs Jahre lang mit der allgemeinen Stromversorgung in dem Gebäude mitgelaufen, die meisten hätten das Ende ihrer Lebensdauer erreicht, hatte Flughafensprecher Hannes Stefan Hönemann am Donnerstag erklärt. Die Austauschaktion soll rund eine halbe Million Euro
Congratulations @lipovonotres! You received a personal award!
You can view your badges on your Steem Board and compare to others on the Steem Ranking
Do not miss the last post from @steemitboard:
Vote for @Steemitboard as a witness to get one more award and increased upvotes!
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit