Savar's skin artillery project. This initiative is meant to shift the unplanned tanneries of Lalbagh to a healthier place. The project was taken in 2003. The project was about to complete the three-year project in 2005. The approved allocation was 175 crore 75 lakh taka Increasingly allocation has increased to Tk 1,787 million 71 lakh. Expenditure increased 902.96 million taka The three-year project has been completed in 17 years. By the end of the last two more years, the project has been fixed for June 2019. On paper, 90% of the work has been done so far. The government is stupid in this regard, but the government is silent.
An analysis of the expenditure on leather industrial projects, the cost of building fire service stations has been increased from Tk 17 lakh to Tk 1.03 crore in the purchase of building, fire-fighting vehicles and equipments. The repairs and maintenance costs have been increased from Tk 75 lakh to Tk 2.56 crore. Dumping yard for solid waste management has been raised from Taka 4 crore to three times to 12 million taka. The cost of construction of water supply system has been increased from Tk 25 crores to 27.33 million taka. The main gate was about to do one. It is now being done two. The cost of a gate is 15 lakh 15 thousand taka. Now the cost for two gates has been one crore taka. The compensation amount has been kept at Tk 10 crore three lakh.
According to the project proposal, the unplanned tanneries were so long in the densely populated Hazaribagh area of Dhaka. There was no system of scientific management of waste in the area. As a result, public life was severely disastrous. So, in December 2005, the project was approved by ECNEC for the transfer of factories in December 2005 at the cost of 175 crore 75 lakhs. Hazaribagh's 154 factories got land allotted in this city. Even after giving guidance from the High Court, the industrial town is still not ready. The number of industrial units allotted by 205 plots on about 200 acres of land is 155.
After one year of approval, the expansion of the project was extended by one year to December 2006. After six months it was extended again. With no foreign assistance during the project, expenditure of Tk 545.36 crore has been increased to three and a half years till June 2010. After that, new organs are added to the project. Project CETP, dumping yard, water extraction, refining and supply system could not be completed by June 2010. As a result, according to the proposal given to the Planning Commission, the expiration was again extended to two years. After 10 years, the cost of the project was increased to Taka 1,787.17 million. Even after a year the extension was extended twice, which ended in June last year. But the project was not completed after two years was extended again.
According to the report made by the Ministry of Industry, 153 out of 155 factories submitted their lay-out plan. All the layouts have been approved. According to approved le-out plan, 143 industries have already started construction of their factories. The construction of the remaining 12 plots was postponed due to the trial and the high court's observation. On the other hand, 53 tannery industries have set up tanning drums. 130 tanneries have applied for permanent electricity connection. 120 industries have applied for gas connections. Process of gas connections in two establishments is underway. 45 institutions have applied for water connection. 42 industries have been given water meters.
Congratulations! This post has been upvoted from the communal account, @minnowsupport, by csdchad from the Minnow Support Project. It's a witness project run by aggroed, ausbitbank, teamsteem, theprophet0, someguy123, neoxian, followbtcnews, and netuoso. The goal is to help Steemit grow by supporting Minnows. Please find us at the Peace, Abundance, and Liberty Network (PALnet) Discord Channel. It's a completely public and open space to all members of the Steemit community who voluntarily choose to be there.
If you would like to delegate to the Minnow Support Project you can do so by clicking on the following links: 50SP, 100SP, 250SP, 500SP, 1000SP, 5000SP.
Be sure to leave at least 50SP undelegated on your account.
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit