today I will explain the procedure or method of implementation of the headmaster's office work, here I do not explain about the volume for material needs and price per material, but today I am more focused and more detail with the method of stages implementation of the work.
The purpose of this building work is for the principal's room and the teacher's staff, given the inadequate school conditions and the lack of classroom needs in class activities and the need for unavailable office space. Then from the local government have also conducted a survey and review to the location, so by taking the policy of the City Government Lhokseumawe also to relocate funds 250.000.000 rupiah, or more funds is equivalent to $ 19,000. for one unit of headroom building of SDN.12 Blang Mangat,
in the stages of implementation of the work that we must consider is the steps from the beginning of the job to finish the work for the building,
As for the method of implementation of the work are:
land clearing work
In this first job we must do because every building that will be in the building must be seen whether there are trees, big rocks and others. then we have to clean it so that it is not blocked.Work of bowplank wood placement as a reference The main point,
in this work must Determine Zero point or as Building point by using wood and yarn to show the building area, and also by using coordinate point or GPSLand excavation work.
In this excavation work should be dug as deep as 80cm This aims to create a cyclope foundation, because if the building was no foundation then the building will collapseA Sand work
This sand work is used as a base at the base of the foundation so that cast concrete for the foundation is not directly attached to the soil, so that the concrete will be more awake.Cyclope foundation
The foundation work in this building is to withstand the burdens that exist on this Cyclope foundation, as this is the main force of the building's working phase.Works SLOOF concrete
This sloof work aims at binding each other between the concrete columns with the sloof and holding the brick load on it.Concrete column work
The work of this reinforced concrete column is as a concrete structure for buildings by means of reinforced concrete casting, aims to strengthen the structure of this building.The work of brick pairs
The purpose of the masonry work is as a retaining wall and part of the construction and for the restriction of the space separator.The work of reinforced concrete beams is
This reinforced concrete structure is a component in the building, this Rink concrete beam can withstand loads that work on building structures and also to bind each endpoint of reinforced concrete columns, Work Prior to concrete block Rink there are several stages of work that is the installation of iron and installation of formwork and after that done casting with 1: 2: 3 concrete so the demolition stage formwork.Installation of light steel frame work (zingkalum)
This work is to withstand the load of the zinc roof cover, ie the roof load itself and also the wind load and rainwater load. then the roof of the zinc in pairs and tied with nut bolts in the frame of light steel horses. If this lightweight steel frame rod does not yet exist, but the zinc roof can not be installedRoof covering work
Zinc roof also serves to withstand wind loads and can withstand rainwater loads and prevent water from entering into the room, this zinc roof uses a type of zinc-coated steel material, metal and with a beautiful red color so the building looks beautiful and nice.Ceiling Work
Ceiling work is intended to cover the ceiling in the room or outdoors so it looks nice and beautiful and easy when installing lamps and wood profiles, the type of material or material often used is Trilplex T: 4mm.Mortal Cement Plastering Works
This works for brick wall coverings so that the walls look neater and smooth the surface of the walls, then the bricks are also more durable for this building.The work Glass windows and wooden panel doors
The work of installing glass windows and wooden panel doors, part of this work includes the final stages of finishing, because the glass windows and wooden panel doors are ready to be made in the carpenter's workshop for easy and fast installation in this building.Ceramic floor work
In this work should be done slowly with patience and thoroughness because in this ceramic work should not occur ceramic or broken. and with some mortar cement for ceramic installation it must be completely filled with mortar cement so there is no gap under ceramic floor, either the base surface or the back side of the ceramic.Wall paint work and ceiling
In this wall paint work and ceiling ceiling must first be in basic paint with white color, so when the second paint more pervasive and thicker the paint so it looks more beautiful and beautiful.Electrical installation work
This work is also the last stage of the job of installing power lines and some switches, sockets, light fittings and lights. so that the installation of electric current can work and can be used.Final cleaning work
This work is a cleansing stage of pieces, wood, zinc, light steel frame, iron, and bricks and others.
then this is the stage of implementation of this building work, so the work can be completed and can be used for the school leadership room and also used for the teachers' work space.
Below I will show you some of the photos I have taken with my camera, from these photos can be simplified and clearly visible from each one I have written above and several stages of working methods in this building.
this photograph shows the results of excavation of soil for foundation work completed by human worker, in this work process the size of the volume in the excavation of the soil and by the size of the width, the height of excavation and the overall length of this excavation is in accordance with the drawings in the field and also the volume calculation. so the workers for this digging are easy and clear to do so.**
**
In this photo, the foundation has been completed, the concrete foundation is also mixed with cement and with the stone stones in it so that the foundation remains strong, because this foundation is very instrumental in all the strength of this building
This is the work of brick walls, iron for columns, and the job of mounting wooden door frames for doors. the workers also do the work and with some sides of the brick wall, at this stage also installed some wooden frames for windows, but there are some unfinished brick walls employed by workers. In the work of sloof beneath the brick wall has been done 100%, because the work of reinforced concrete is not too long in doing, it's just a matter of waiting until the water quality of concrete hardens and then can be done the brick work stage.
At this stage of work, the masonry work is done up to 100%. But plaster brick walls with mortar cement is not done.
In this photo for the type of concrete beam is also done by way of casting reinforced concrete. So for a few days other work must wait until the job is completely dry until the concrete is hard.
This is the stage of execution of stucco work that includes brick walls indoors and outdoors. on the columns and beams in aci with the water cement factor (aci), but the brick wall coverings have finished work on each side of the brick wall. And plus some kind of work like sand floor and others.
This photo shows the stages of light steel frame work for zinc roofing, this phase of work also takes up to 4 working days, because the material is too far from the location, so that too long too, in this stage I have explained above on how to plug the framework light steel.
Photos from the side of the right side of the building is also seen the stage of installing the steel frame has been completed.
This is a photo of the brick wall paint stage, this stage also I have described above in the implementation phase of the work.
Photos Implementation of work for this building has finished 100% doing the work. and looks with the look of various sides and with nice and beautiful colors.
By. @aguess
if no objections from the #steemstem I use the logo about science and #engineering thank you very much #steemstem
thank you for all your support and have seen my work, though not much changed with $ in this post, but I will remain optimistic with what is my priceless post .. thank you very much ...
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
nice simple building ..
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
Thanks..
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit