Good evening Steem world! This is the first day of the week but this is the last day of being in the Operations Department. Despite of that, the next departments are still on-site so my skin will still be as dark as ever. 😢
We went to tower 4 first to check the columns if they are ready for cementing. First thing I noticed is the gravel floating above the concrete. It means that the sand did not mix properly with the cement mixture.
Then they are assembling the scaffolds already ready for the 2nd floor of the building
We also counted the steel rods of the column if they are properly placed and the number of it is okay.
Some spacer walls
And the view of the site from the 2nd floor scaffolding of tower 4
We also climbed the roof deck again
Soon to be elevators
And here is the fire exit of tower 1 from the roof deck
And the view of the underground of tower 3 while we are walking back the office
So that's all for the last day of operations. Thank you for reading!
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
I love this work. So detailed and articulated. Thanks for sharing.
I am me @brightfame
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit
Thank you
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit