After long wait final I got job in power substation .It is my first experience.to work in such a heavy risky area..
220kv power incoming supply..Coming from hoody substation and we r stepping down to 11kv by using 40mva transformer
And distributing to total of 13 no software building..
I m learning lot from this new job.
Previously I worked in building inside Lt side..ie 3phase and single phase.. now it's 220kv lots of procedure we have to follow
Our yard is old so we have sf6 3100 amp circuit breaker. Every day we have to check lighting arrestor staus oil level in ct and gas and air pressure in sf6 breaker. And also leakage .
And also check 49mva transformer staus . Breather colour conservator tank oil level bushing oil level . Any oil leakage. Oltc count and also oltc tap position.
Evey 4 hour we have to take incoming and outgoing reading. And also check all normal indicators working properly in panel.
Thanks for. Reading ..... Tomorrow I will post my 2nd day experience.
Please like share upvote and support my work
Congratulations @shivaprasad! You received a personal award!
You can view your badges on your Steem Board and compare to others on the Steem Ranking
Do not miss the last post from @steemitboard:
Vote for @Steemitboard as a witness to get one more award and increased upvotes!
Downvoting a post can decrease pending rewards and make it less visible. Common reasons:
Submit